Semi-high-speed train line

Why is it in news?
  • Recently the Kerala government informed the NITI Aayog that the semi-high-speed rail SilverLine, estimated to cost Rs. 63,941 crore, is viable and feasible.
  • The cost per kilometre would be of Rs. 120.77 crore for laying the corridor.
Details:
  • The semi-high-speed rail SilverLine is of 529.45 km and will run from Kochuveli to Kasaragod.
  • The project awaiting Central clearance.
  • The cost of land along the National Highway and through interior areas wasRs. 18 crore per hectare and Rs. 9 crore per hectare respectively.
  • The process of granting administrative sanction for land acquisition had commenced.
  • Around 80% of land would be acquired within 18 months.
  • The detailed project report (DPR) had been prepared.
  • Maximum possible revenue generation would be explored.
  • The project was said to be self-sustainable.





Posted by Jawwad Kazi on 29th Nov 2020